Yazd Water and Wastewater Company Call for prequalification For Financing, Construction, Operation and transfer of A Section of Yazd city Water Supply Facility in the frame of B.O.T. contract second TIME The Yazd Water and Wastewater company intends to procure the financing, construction, operation and transfer of a section of Yazd city water supply facility through […]
Yazd Water and Wastewater Company
Call for prequalification
For Financing, Construction, Operation and transfer of
A Section of Yazd city Water Supply Facility in the frame of B.O.T. contract
second TIME
The Yazd Water and Wastewater company intends to procure the financing, construction, operation and transfer of a section of Yazd city water supply facility through a B.O.T. (Build-Operation-Transfer) Contract and in the frame guaranteed purchase of water according to item “a” Article (142) of the Law for the Fifth Development Plan and Guideline 27 of the Law for annexation of some articles to the law on drafting part of the government’s financial regulations (2) on conditions for concession of new, half-completed and ready for operation capital asset acquisition plans to private sector (approved on 26th September 2015), through competitive bidding according to the relevant laws, regulations and executive orders as per the following conditions to the qualified investor.
A-Brief description of the project
– Estimated capital investment of the plan: 1.900.000.000 IR.Rials.
– Construction period: 36 months
– Commercial operation period: 25 years since facility construction period finished
– Offtake purchaser: Yazd province water and wastewater company on behalf of Power ministry of enrgy whereas guarantee the purchasing of transmitted water according to the listed quality conditions in documents in the contract period, through guarantee purchasing credit tier according to item “a” Article (142) of the Law for the Fifth Development plan of the country.
– Production capacity (Volume of annual transmitted water): 67.10 milion cubic meter (increase stepwise from 58.21 million cubic meter up to year 2031)
– Aim of the project: Drinking water transmission from water resources to the urban water reservoirs, links between main reservoirs and main water supply lines
– Location of project: Iran- Yazd Province- Yazd City
– Scope of work (The main components of the project): ۱– Financing ۲– Engineering and design services ۳-Materials Supply ۴– Construction of reservoirs (7 units, total volume of 131000 cubic meter) ۵– Supply of pipes, valves and accessories ۶– implementation of water transmission lines (a length of 116 km, 400 to 1600 mm in diameter of iron ductile and GRP) ۷– Supply, shipment and installation of all electromechanical, control and instrumentation equipment ۸-Construction of one pump station with capacity of 1427 liter per second ۹– construction of 6 sets of water disinfection plant ۱۰– Overhaul of the project ۱۱– Construction of required access roads ۱۲– Power supply ۱۳– Commissioning and performance test ۱۴– Operation and maintenance for 25 years ۱۵-Transfer Constructed facilities to offtake purchaser after commercial operation period
– Offtake purchaser consultant: Consultant: ARNA Strategic Planning and Development Consulting Engineering Company
B- Investor’s requisites: Possibility to ensure the required financing and adequate experience in the management, execution and operation of similar projects
If any foreign investor desire to participate in the tender an Iranian company should be one of the main joint venture stakeholders.
۱- Qualified investors may collect the prequalification documents from address: Bureau for Contractual Affairs, Yazd province Water and Wastewater company, Ayat-Allah Kashani St , Yazd city, Iran (Phone: +98-35–3164156 or 3164115) or website “www.iets.mporg.ir” or “www.abfayazd.ir” by presenting introduction letter and bank receipt (Amounted 300000 Rials to current account with the 2046528.64 bank in the name of Yazd province Water and Wastewater company) until dated 14.may.2016 from the publication of this notice in the paper and complete and submit the said documents in a sealed envelope maximum by dated 30/05/2016 at 14 O,c to the following address against a signed receipt.
۲- The submitted envelopes shall be opened on Dated 31/05/2016. At, Yazd province Water and Wastewater company
– Following the review of the evaluation documents submitted by the interested parties, thequalified investors shall be invited for contract negotiations.
– The concessioner has the right to accept or reject the technical or financial proposals of the investors at any stage of the proceedings.